25.To crash a project most effectively, additional resources or overtime should be assigned to
which of the following?
A.All tasks defined in the WBS (Work Breakdown Structure)
B.Those activities that match the skill set of the additional resources available
C.The activities with the greatest degree of risk according to risk management
D.Activities along the critical path starting with those longest in duration
Correct:D
26.Given limited time and resources to execute a set of projects, what is the BEST way to proceed?
A.Prioritize all projects equally
B.Prioritize the projects based on what each sponsor requests
C.Prioritize the projects based on management consensus
D.Prioritize the projects based on what the project manager thinks is best
| English | Chinese(Traditional) | Chinese(Simplified) | 7
KillTest
Information Co., Ltd. All rights reserved.
Correct:C
100% Guarantee to Pass Your Project+ exam and get your Project+ Certification.
We guarantee your success in the first attempt. If you do not pass the Project+ PK0-002 (IT Project+ Certification (2003 Objectives)) on your first attempt we will give you a FULL REFUND of your purchasing fee AND send you another same value product for free.
killtest PK0-002 Downloadable.
Printable Exams (in PDF format) Our Exam PK0-002 Preparation Material provides you everything you will need to take your Project+ exam. The Project+ Certification details are researched and produced by Professional Certification Experts who are constantly using industry experience to produce precise, and logical. You may get Project+ exam questions from different web sites or books, but logic is the key. Our Product will help you not only pass in the first Project+ exam try, but also save your valuable time .