7.If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?
A.The high level budget estimates are inaccurate
B.The organizational spending plan is inaccurate
C.The budget is not aligned with the spending plan of the organization
D.The detailed bottom up budget will need to be adjusted
Correct:C
8.The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate
Quality Management technique to implement?
A.Evaluate phase exit milestones using sufficiency criteria
B.Flexible entry and exit criteria to minimize schedule delays
C.Quality measures reported only to the project steering committee
D.Many work teams with few members to maximize the number of deliverable handoffs
Correct:A